Biratnagar Airport’s New Terminal Reaches 81% Completion

Biratnagar Airport’s new terminal building has reached 81% physical completion, with construction targeted to finish by mid January 2027. The project in the Biratnagar aims to modernize passenger facilities at one of eastern Nepal’s key airports, with a three storey, technology friendly terminal designed to improve passenger convenience and upgrade existing infrastructure. The development is expected to provide a more modern environment for passengers using the airport.

The Rs. 3.12 billion project began in December 2022 and includes improvements intended to make the airport’s terminal and related physical structures more earthquake resistant. Once completed, the expanded facilities are expected to increase the airport’s aircraft parking capacity from five to seven. The upgrade is part of the airport’s broader infrastructure development, although the source does not specify any planned changes to flight schedules.

Modern Terminal Designed to Improve Passenger Facilities in the Airport

The new terminal building is being constructed with passenger convenience and safety in mind. According to Sanjiv Khadka, information officer at Biratnagar Airport, the three storey building covers approximately 18,000 square metres and is designed with modern technology and updated facilities. Its expanded layout is intended to support airport operations and provide improved facilities for travelers.

The project forms part of efforts to upgrade the infrastructure of Biratnagar Airport, which has been operating since 1958. The airport has an overall area of approximately 122 bighas, while its runway measures 1,775 metres in length. These existing facilities make the airport an important part of the region’s air transport network.

Rs. 3.12 Billion Project in the Airport Nears Completion

Construction in the terminal of the airport began in Poush 2079 (December 2022 – January 2023), with a total estimated cost of Rs. 3.12 billion. The project includes the construction of the new terminal and improvements to existing airport infrastructure, with earthquake resilience identified as an important objective. The investment is intended to provide more modern airport facilities while strengthening the infrastructure for long-term use.

Biratnagar Airport’s New Terminal Reaches 81% Completion

With physical progress now at 81%, construction is targeted for completion by Poush 2083, which falls around mid January 2027. The remaining work will be important in bringing the new terminal into operation, although the report does not specify an opening date. Meeting the deadline will be a key step toward delivering the planned improvements to the airport.

Aircraft Parking Capacity to Increase

Biratnagar Airport currently handles approximately 20 to 25 flights daily, according to Khadka. The airport presently has parking space for five aircraft, and the new terminal project is expected to expand this capacity to accommodate seven aircraft. The increase would provide additional parking space as part of the airport’s infrastructure upgrade.

The additional parking capacity and upgraded passenger facilities are intended to strengthen the airport’s infrastructure. However, no new flight routes or increases in flight frequency have been announced in the source report, and the project’s direct impact on tourist arrivals remains unconfirmed. Any future operational changes would depend on decisions beyond the construction project itself.

Biratnagar Airport’s Long Operating History

Biratnagar Airport began operations in 1958 and has served as an important aviation facility in Koshi Province for nearly seven decades. Its development received assistance from the governments of India and South Korea, according to the source report. Since its establishment, the airport has remained part of the region’s air connectivity infrastructure.

The ongoing terminal project represents a major infrastructure upgrade for the airport. While the improvements may support passenger travel in eastern Nepal, the report primarily concerns airport construction rather than a specific tourism initiative. The completion of the project is expected to mark a new phase in the airport’s physical development.